PART 1: Laying carbon steel pipeline
(FLOW LINE) dia. 8 inch from Christmas tree to the many full included 18 line each line with length of 8 km dia. (6-8 inch).
The work included
1- Construct service roads 10 m width.
2- Excavate trenches (1.5 m deep * 1 m width).
3- Laying the pipes through the main
street and rivers by HDD way.
4- Install many full (3 No.) with capacity of 6 wells for each.
PART 2: laying carbon steel
transportation line (TRUK LINE) (3 No.) dia. 16 inch from many full to CPF1 in total length 20 km for each line. Laying the pipes through the main street and rivers by HDD way.
All the works of project-included
installation, wilding, fabricate and
connections with all NDT test.